Boiler installation certificate: what you should get and what to do if it is missing
The boiler installation certificate most people mean is the Building Regulations Compliance Certificate. When a Gas Safe registered engineer fits a new gas boiler in England, they notify the work to Gas Safe Register, which tells your local authority building control and posts the certificate to the householder. The engineer has 30 days from finishing the job to make that notification, so the certificate arrives by post a few weeks after the install, not on the day. Keep it with the commissioning checklist from the boiler manual. You will need both for the manufacturer's warranty, and a buyer's solicitor will ask for them when you sell.
Loyal Plumbers · Updated
Discuss a boiler replacementThe paperwork you should have after a new boiler
A new boiler comes with more than one document, and they are easy to confuse. Each one proves something different, so it is worth checking you have all of them before the installer's final invoice is settled.
| Document | Who provides it | What it proves |
|---|---|---|
| Building Regulations Compliance Certificate | Gas Safe Register, by post, after the engineer notifies the work | The installation was notified to building control through a competent person scheme |
| Benchmark commissioning checklist | The installing engineer, completed in the boiler manual on the day | The boiler was set up and tested to the manufacturer's instructions; usually needed for warranty |
| Manufacturer warranty registration | The installer or you, with the manufacturer | The warranty period and its conditions, such as annual servicing |
| Gas safety record (CP12) | A Gas Safe registered engineer, on each annual check in rented homes | The appliances passed a gas safety check on that date; not an installation certificate |
A gas safety record is not the same thing as a Building Regulations certificate. Landlords need an annual gas safety record whatever the age of the boiler. Our guide to the gas safety record versus installation record explains the difference in more detail.
Why the certificate matters
Fitting or replacing a gas boiler is notifiable building work. Using an engineer registered with a competent person scheme, which for gas is Gas Safe Register, means you do not have to apply to building control yourself. The certificate is the evidence that this route was followed.
It matters most when you sell. The standard property information form asks about boiler installations and certificates, and a buyer's solicitor will usually want to see the compliance certificate for any boiler fitted since the rules came in. A missing certificate rarely stops a sale, but it can slow it down while you chase it. If you are on the other side of the sale, our plumbing checks before buying a house guide covers what else to ask about.
It also helps with warranties and insurance claims. Manufacturers generally want proof the boiler was fitted and commissioned by a Gas Safe registered engineer, and a completed Benchmark checklist together with the compliance certificate is the simplest way to show that. Our boiler warranty vs guarantee guide explains the conditions that usually come with a new boiler.
How long it takes to arrive
The engineer must notify the installation within 30 days of completing the work. Once Gas Safe Register has processed the notification, the certificate is posted to the address where the boiler was fitted. In most cases it arrives within a few weeks of the install.
If it has been more than a month or two and nothing has come, ask your installer to confirm the date they notified the work. Occasionally the notification is delayed, or the certificate is sent in the name of a previous occupant or to the wrong flat number in a converted building.
If your certificate is lost or never arrived
Work through these in order. Most missing certificates turn up at the first or second step.
- Check the folder that came with the boiler, and any post addressed to the property around the time of the install, including post for previous owners
- Ask the installer for the date they notified the job and the reference, if they still trade
- Contact Gas Safe Register with the address and approximate installation date to ask whether the work was notified and to request a replacement certificate; there may be a charge
- Ask your local authority building control whether they hold a record of the notification for your address
- If the work was never notified, speak to building control about regularisation, and let your solicitor know if you are selling
What if the boiler was fitted without being notified?
If the installation was never notified, the most likely explanation is that the installer did not register the job, or that the person who fitted it was not Gas Safe registered at all. The second possibility is a safety question first and a paperwork question second.
Have the boiler, flue and gas supply checked by a Gas Safe registered engineer. Illegal gas work can hide faults you cannot see, such as a flue joint that is not sealed or a boiler that was never combustion tested. If anything is found, the engineer will explain it and, where there is an immediate danger, make the appliance safe.
For the paperwork, building control can advise on a regularisation certificate for unauthorised work. When selling, solicitors sometimes deal with a missing certificate through indemnity insurance instead. That is a legal and conveyancing decision, not a plumbing one, so take your solicitor's advice on it.
If you smell gas, or a carbon monoxide alarm sounds, leave the property and call the National Gas Emergency Service on 0800 111 999. Do not wait for paperwork questions to be settled.
Getting a new boiler fitted with the paperwork in order
Loyal Plumbers handles boiler replacement across London and everywhere inside the M25, with gas work carried out by Gas Safe registered engineers. The installation is notified as the rules require, and the commissioning checklist is completed before we leave so the warranty can be registered.
If you are comparing quotes, ask each installer who notifies the work, who registers the warranty and what paperwork you will receive. Our guide to comparing boiler quotes lists the other questions worth asking. To book a survey or ask about an existing installation, call us or send an enquiry with the boiler make, rough age and what you need.
Common questions
- Who sends the boiler installation certificate?
- Gas Safe Register posts the Building Regulations Compliance Certificate to the property once the Gas Safe registered engineer has notified the installation.
- How long does it take to get a boiler certificate?
- The engineer has 30 days from completing the work to notify it. The certificate follows by post after that, so it usually arrives a few weeks after the install.
- Can I get a copy of a lost boiler certificate?
- Yes. Gas Safe Register can check whether the installation was notified and issue a replacement, and there may be a fee. Your local authority building control may also hold a record.
- Do I need a boiler installation certificate to sell my house?
- It is not a legal bar to selling, but buyers' solicitors usually ask for it. Having the certificate ready avoids delays and questions about whether the work was done by a registered engineer.
- Is a gas safety certificate the same as a boiler installation certificate?
- No. A gas safety record (CP12) confirms appliances passed a safety check on a given date and is needed every year in rented homes. The installation certificate confirms the boiler fitting was notified under the Building Regulations.
Sources and further reading
Need help with this in London?
Emergency repairs, investigations and planned installations across London and inside the M25. Tell us what you need so we can agree the next step.
Discuss your job